> My context: I manage projects with several resources and it would be a help to visualize the non working time of people on same Gantt view than the overall project.
> b) second need, 'NWT' defined in a resource calendar for example, let's say that 'Ben' will not work on next Monday, > -> that's the aspect covered by Steve's answer -> ok, solved ! > a) first need, 'NWT' defined in Calendar associated to current project > - I would like to display Non-Working Time (let's say NWT) in Gantt view In fact I have a related need and a related question to solve: